Identify the marketing critical path

Question addressed

Which sequences have no schedule margin?

Direct answer

The critical path connects tasks and validations whose delay moves the final date, while showing the available margin elsewhere.

Decision supported

01Protect the resources and decisions that condition the date.

02The rule, the evidence and the next review date stay visible.

How to use this

Move from the question to the deliverable.

01Starting point

Which sequences have no schedule margin?

02Decision prepared

Protect the resources and decisions that condition the date.

03Deliverable to use

Critical path

Calculation · SQ-11

Calculate a critical path of 19 days

The critical path is the chain of activities without float. Delaying one of them moves the final date, unless the network changes.

Working context

Simplified costed case: seven activities preparing a launch.

  1. 01Network

    Link each activity to its direct predecessors.

  2. 02Move forward

    Calculate the earliest start and finish from the first activity.

  3. 03Move backward

    Calculate the latest start and finish from the final date.

  4. 04Deduce

    Identify the activities whose total float is nil.

Original element

CPM network of the launch

The path A → B → C → G sets a minimum duration of 19 days. D, E and F have limited float.

Calculation methodTotal float = latest start − earliest start
IDActivityDurationPredecessorEarly startEarly finishFloatCritical
AResearch5 d050Yes
BMessaging4 dA590Yes
CCreative8 dB9170Yes
DLanding page5 dB9143 dNo
ETracking3 dD14170Co-critical
FLegal6 dB9152 dNo
GLaunch2 dC, E, F17190Yes
Decision interpretation

01A, B, C and G have no float at all.

02The D → E branch consumes all its float if the landing page exceeds five days.

03Shortening F by one day does not change the final date; shortening C by one day brings it to 18 days.

Teaching example. The calculation assumes deterministic durations and does not replace a risk analysis.

Coherence controls

Minimum conditions before validation.

01No loop

The status, the evidence and the owner must be available for review.

02Realistic milestones

The status, the evidence and the owner must be available for review.

03Owners present

The status, the evidence and the owner must be available for review.

04Explicit buffers

The status, the evidence and the owner must be available for review.

Usable deliverable

Output produced

Critical path