Framework 08 / 12

Assign decision rights, ownership and review rules

Decision question

Who must make which decision, when, and with what information?

Decision

Establish responsibilities and the decision path.

Distinguish who executes, who decides, who contributes and when escalation is required. This step produces reviewable commitments and flags information that remains too fragile to justify a trade-off.

Expected outputs

01RACI

02Decision matrix

03Review calendar

04Escalation rules

Original chart · SQ-37

Measure the latency of plan decisions

Governance is also assessed by the time required to make a decision. Excessive latency consumes roadmap slack.

Working context

Illustrative dataset of 24 decisions made during one quarter.

  1. 01Timestamp

    Measure the request, dossier completeness and decision dates.

  2. 02Segment

    Compare latency by type, threshold and decision body.

  3. 03Diagnose

    Separate waiting for information from waiting for a decision-maker.

  4. 04Reduce

    Adjust thresholds, cadence or delegation.

Original element

Median latency by decision type

Scope changes exceed the target time and consume a median five days of slack.

<€25k
2 dTarget 3 d
>€25k
8 dTarget 7 d
Scope
12 dTarget 5 d
Milestone
4 dTarget 5 d
Stop
9 dTarget 5 d
DecisionVolumeMedianTargetDominant cause
Reallocation <€25k82 d3 dCompliant
Reallocation >€25k48 d7 dIncomplete dossier
Scope change512 d5 dDecision-maker unavailable
Milestone shift44 d5 dCompliant
Initiative stop39 d5 dLate sunk costs
Decision interpretation

01Delegating minor scope changes reduces the main bottleneck.

02Major reallocation dossiers must include a recommended option before scheduling.

03Latency must be monitored as a roadmap risk, not only as an irritation.

Fictitious data. Measurement starts when the dossier is declared complete to distinguish preparation from decision.

Minimum controls

What the plan must make visible.

01One accountable owner

Status, evidence, owner and next review date.

02Available decision maker

Status, evidence, owner and next review date.

03Defined cadence

Status, evidence, owner and next review date.

04Defined escalation

Status, evidence, owner and next review date.