Comparison · C71

Compare sequencing methods

Question addressed

Should the roadmap be sequenced by dates, dependencies, cost of delay or constrained capacity?

Direct answer

The method depends on scope stability, dependency density, delay cost and resource substitutability.

Decision supported

01Choose the primary method and complementary roadmap control.

02The rule, the evidence and the next review date stay visible.

How to use this

Move from the question to the deliverable.

01Starting point

Should the roadmap be sequenced by dates, dependencies, cost of delay or constrained capacity?

02Decision prepared

Choose the primary method and complementary roadmap control.

03Deliverable to use

Four-method comparison

Critical comparison · SQ-71

Choose the sequencing method by the dominant constraint

A calendar of dates is visually reassuring but often hides dependencies and bottlenecks. The method must reflect what makes a delay costly or irreversible.

Working context

Comparison applied to a launch roadmap with 22 tasks, six strong dependencies and two critical roles.

  1. 01Diagnose

    Measure the stability of dates, the density of dependencies, the cost of delay and the scarcity of roles.

  2. 02Compare

    Assess the methods on the same portfolio and the same assumptions.

  3. 03Choose

    Keep one main method and one complementary control.

  4. 04Revise

    Change method if the dominant constraint changes during execution.

Original element

Dates, critical path, cost of delay or constrained capacity

A method scores highly when it makes the constraint concerned explicitly visible.

MethodDependenciesCost of delayScarce capacityReviewUse
Date-based calendar1/51/51/53/5Simple communication
Critical path5/52/52/53/5Stable dependencies
WSJF / cost of delay2/55/53/54/5Competing options
Critical chain4/53/55/54/5Constrained resources
Decision interpretation

01The critical chain is retained because marketing ops and product marketing limit several tasks at the same time.

02The critical path stays in use to control the six non-negotiable dependencies.

03A calendar of dates is produced for communication, but does not serve as a decision algorithm.

Methodological comparison. The methods lose their value if durations, dependencies and capacities are not kept up to date.

Coherence controls

Minimum conditions before validation.

01No loop

The status, the evidence and the owner must be available for review.

02Realistic milestones

The status, the evidence and the owner must be available for review.

03Owners present

The status, the evidence and the owner must be available for review.

04Explicit buffers

The status, the evidence and the owner must be available for review.

Usable deliverable

Output produced

Four-method comparison